Whittington Master Plan

 

Whittington is designed in 3 phases. Phase I includes the entrance, the R2 lots 123 – 155 in yellow, and the R4 lots 21 -25 and 80 – 87 in magenta. The purple RE-B lots 88 – 93, 111 – 114, and lot 122 are also included in Phase I. In Phase II the RE-B lots 94 – 110 and 115 – 121 complete the RE-B lots planned for the development. Phase III will be broken up into multiple construction stages. The R4 lots 26 – 79 in magenta, will be the initial construction stage starting in late 2019. The yellow R2 lots 1 – 20, will follow sometime after the initial construction stage. The pool is planned in Phase III on lots 43 and 44.